ROYAL MINT GARDENS

Client: IJM
Value: £8.8m
Location: Tower Hill
Duration: 9 months

These core works were in a live railway environment to encapsulate an existing DLR cutting using pre-cast beams with a concrete structural topping. The installation of the encapsulation has created a DLR tunnel environment in turn requiring further works trackside to meet DLR tunnel environment standards.

Works included, full electrical and mechanical installation along the full length of the 150m tunnel. Two escape routes along the North and South of the encapsulation with a steel framed walkway and GRP handrail. 100m of Pre-cast plank installation with structural slab topping. Install electrical and mechanical plant room for all control gear. Western and Eastern Barrow crossings installed for services to cross the tracks.